Power generation suspended from second unit of Vallur plant.

Generation from one of the three units of the Vallur power plant, jointly set up by NTPC and the Tamil Nadu Government, has been suspended due to shortage of coal, official sources said.

'Power generation has been suspended from the second unit for the last two days. It is mainly due to coal shortage,' an official told PTI.

'Power has been generated to about 400MW from the first unit and due to the shortage of coal, work has been suspended from the second unit,' he said.

Asked about the third unit, he said it was working.

It was expected that the second unit would resume operations soon.

HBL


OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software