Published On:August 21 2014
Story Viewed 1846 Times
KSTP Phase II work on the slow lane in Thiruvananthapuram.
The delay in getting the mandatory clearances from various agencies, shifting of utilities, and resistance from residents have resulted in the slow progress of the World Bank-funded Kerala State Transport Project (KSTP) Phase II.
Three road corridors, of the eight, taken up when the second phase was kicked off in June 2013 had missed the completion target set for February 22, 28, and April 28 this year under the first milestone due to the delays, official sources told The Hindu.
The corridors taken up were Kasaragod-Kanhangad (27.78 km), Pilathara-Pappinissery (20.90 km), and the 54-km Thalassery-Valavupara stretch. Only 10 per cent of the work had been completed, sources said.
The clearances from the Kerala State Pollution Control Board, Mining and Geology Department, and the Local Self-Government Department were awaited, they said.
Following the delay in cutting trees and resistance from residents, two contractors had sought the extension of deadline.
Over 95 per cent land acquisition for the second phase was completed during the first phase of the KSTP itself, initiated with World Bank aid in 2002. As many as four corridors had not been awarded, sources said.