Published On:January 21 2014
Story Viewed 1608 Times

Mega Plan to Generate Power from Sewage.

In its efforts to minimize power bills, Bangalore Water Supply and Sewerage Board (BWSSB) is preparing a road map to generate 100 MW of power from over 1,000 MLD of sewage generated in the city.

BWSSB Chief Engineer S Krishnappa said, 'As we are consuming around 60 million units of power every month, we are incurring a lot of expenditure on electricity bills.'

'According to our estimates, we can generate around 100 MW power from the sewage generated in the city. It will be sufficient to meet 75 per cent of our (power) needs.'

14 STPs Identified for Project

Krishnappa said BWSSB has identified 14 sewage treatment plants (STP) where methane gas can be generated from the sewage.

As the STPs are in good condition, BWSSB can start generating methane by constructing a digester near them.

'The biggest challenge is to ensure that the methane generated in the digester is pure in nature. If not, the generator that burns methane will be destroyed very soon,' Krishnappa said.

BWSSB has already initiated the process to produce electricity from sewage at one of the STPs in Hebbal valley by entering into an agreement with England-based Mott MacDonald Ltd.

The New Indian Express


OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software