RPower's 6th Sasan unit on track for commissioning.
Reliance Power said that boiler light up has been achieved for its sixth 660 MW unit of the 3,960-MW Sasan ultra mega power plant in Madhya Pradesh.
Boiler light up is a critical milestone in the commissioning activity of a power plant.
RPower said 3,300 MW (five 660 MW units) of the project are already operational.