Metro rail powered for 30 km, final trials soon.

L&T Metro Rail Hyderabad (L&TMRH) has announced that trial runs between Begumpet to S.R. Nagar via the Ameerpet interchange station are now ready to commence with the Government of India’s Chief Electrical Inspector D.V.S. Raju according sanction for energisation of Overhead Electric Traction System (OETS).

Earlier on Monday, Mr. Raju conducted the statutory inspection of the overhead power systems where electricity is drawn from the 132/25Kv receiving station at the Uppal depot. The incoming supply to this is from the 220/132Kv main substation of TS Transco.

“Energising the traction system will help in commissioning the entire 30 km stretch from Nagole to Miyapur. This will also enable testing of other systems of metro rail,” he said. Trains can now be run from Nagole to Ameerpet to SR Nagar and also from Ameerpet to Miyapur with interchange station at Ameerpet.

Trail runs were completed and safety certification obtained for Nagole to Begumpet and Miypur to S.R. Nagar. Ameerpet station has also got power supply connection last week and it has led to the illumination and functioning of lifts and escalators at the interchange station.

L&TMRH MD and CEO Shivanand Nimbargi has informed that all the statutory requirements will be completed by November 20 to make the system ready for commissioning and inauguration while pointing out that the tests will conclude with the Commissioner of Metro Rail Safety (CMRS) inspections and clearances.

He, along with Anil Kumar Saini, Head, Railway systems of L&TMRH were with Mr. Raju during his inspection along with officials from the Independent Engineer Louie Berger and HMR.

Hyderabad Metro Rail (HMR) will certainly stand out when compared to the other metro projects commissioned or under construction in other cities across the country because it has been laying much emphasis on the facilities down below the stations for convenience of the commuters and pedestrians, affirmed MD N.V.S. Reddy on Monday.

“We are concentrating on improving the road and street infrastructure under the stations so that the contrast of ‘palaces’ built overhead is not too much. We are working on signages, putting railings for the entire station stretch to prevent spillover onto the main thoroughfare, service roads, earmarking of parking space based on vehicles priority starting with public transport buses, electric vehicles, etc.,” he informed.

Mr. Reddy was speaking at the ongoing Urban Mobility conference in the presence of transportation experts and other metro rail MDs when doubts were expressed about how the prevailing traffic chaos on the roads can be contained once the metro becomes operational.

Street furniture and pedestrian circulation areas near some stations where there was sufficient spaces for citizens to move around and relax were also some of the unique features of the project here. Footpaths of widths ranging from 15 ft to 50 ft are being provided at different stretches on both sides of the road, he added.

THE HINDU


OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software