Published On:October 18 2011
Story Viewed 2850 Times

Gamesa, plans 50 MW wind farm in Karnataka

Gamesa, is looking at Karnataka as contributing 'a substantial portion' to the 1,000 MW of wind farm capacity it has lined up across India over the next one year.

As part of this, Gamesa will put up 50 MW of capacity in the State between now and March 2012.

Gamesa, which is primarily in the business of manufacturing wind turbines, also develops wind farms.

Typically, most generating assets in the farm would be owned by different investors - Gamesa's customers and Gamesa would maintain the farm for the investors.

As part of the first phase of 30 MW, the company has just commissioned 7 MW in the last two weeks and expects the entire farm to start generation by March, 2012.

The wind farm is being put up near the town of Chikodi in Belgaum. Gamesa will add another 25 MW from a similar wind farm at Kiroshi, close to Chikodi.

It takes Gamesa roughly Rs 6 crore to put up a MW of wind power, and when the wind farms in Chikodi are fully operational, Gamesa would have catalysed investments of Rs 300 crore into the wind power sector in Karnataka.

The company has used its flagship 850 KW machines and the farm would generate 60 million units of electricity a year.


OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026