'Hold Fresh Study on Coal-fired Power Unit'.
The National Green Tribunal (NGT) has quashed the clearance given to the coal-fired power plant coming up in Cuddalore district, directing the private company to get clearance from the Expert Appraisal Committee (EAC) after carrying out a fresh Cumulative Impact Assessment (CIA) Study.
Following a series of petitions, the matter reached the NGT where it suspended the Environmental Clearance (EC) on May 23, 2012. In its order, the tribunal directed the Ministry of Environment and Forests (MoEF) to review the EC granted to the project based on a CIA study and stipulate any additional environmental conditions if required.
Based on the directive, the MoEF issued a corrigendum on August 14, 2012.