Published On:August 29 2022
Story Viewed 1426 Times

386 infrastructure projects show cost overruns of Rs. 4.7 trillion.

As many as 386 infrastructure projects, each entailing an investment of Rs. 150 crore or more, have been hit by cost overruns of more than Rs. 4.7 lakh crore, as per a report.
According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs. 150 crore and above, out of 1,505 projects, 386 reported cost overruns and as many as 661 projects were delayed.
"Total original cost of implementation of the 1505 projects was Rs. 21,21,793.23 crore and their anticipated completion cost is likely to be Rs. 25,92,537.79 crore, which reflects overall cost overruns of Rs. 4,70,744.56 crore (22.19% of original cost)," the ministry's latest report for July 2022 said.
According to the report, the expenditure incurred on these projects till July 2022 was Rs. 13,50,275.69 crore, or 52.08 per cent of the anticipated cost of the projects.
However, the number of delayed projects decreases to 511 if delay is calculated on the basis of the latest schedule of completion.
Further, it showed that for 581 projects neither the year of commissioning nor the tentative gestation period has been reported.
Out of the 661 delayed projects, 134 have overall delays in the range of 1-12 months, 114 have been delayed for 13-24 months, 289 projects for 25-60 months and 124 projects have been delayed for 61 months and above.
The average time overrun in these 661 delayed projects is 41.83 months.Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.
Delay in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems are among the other reasons.
The report also cited state-wise lockdowns due to COVID-19 as a reason for the delay in implementation of these projects.
It has also been observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported, it stated.
BS




OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Refund & Cancellation Policy | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Ruban Softwares