L&T set to construct Navi Mumbai airport, likely to finish by mid-2020.

L&T set to construct Navi Mumbai airport, likely to finish by mid-2020.

Larsen & Toubro (L&T), a leading player in the airport construction segment, is set to win contract to build the Navi Mumbai International Airport. The board of City and Industrial Development Corporation (CIDCO), the planning authority, met on Friday to consider the contract.

A tender to select the engineering procurement and construction (EPC) contractor was floated last August. A source said L&T has been chosen for the construction work. The contract size is not known and the award will take place following government approvals, it is learnt. “We are yet to award the EPC contract and will share an update in due course,” said a spokesperson of GVK, which is developing the Navi Mumbai airport. A CIDCO spokesperson did not respond to an email query.

An L&T spokesperson confirmed its participation in the bid but did not elaborate. L&T is the project contractor for ongoing expansion works at Bengaluru, Delhi, and Hyderabad airports.

Navi Mumbai airport has been plagued by delays and cost escalation over issues related to land acquisition and environment issues. The airport was being planned to handle 10 million passengers in the phase one, but the terminal will now be built to handle 20 million.

The first phase project cost is pegged at over ~14,000 crore and is being funded through equity investment and ~10,300-crore long-term debt. While the state hopes the airport will be ready by mid-2020, CRISIL in its report in May-end had said operations are expected to start in 2023.

Site complexity is another challenge. One of the first tasks of the contractor will be to raise the ground level to 8.5 metres and laying utilities. These would need to be carried out before the construction of runway and other infrastructure. The contract scope covers cut and fill works, construction of terminal, airfield works, including runway, apron, ancillary buildings, multi-level car park, GVK had said in its bid notice last August.

Pre-development work for the project began in June 2017. This included flattening a hillock, reclaiming marsh land and diverting a river. CIDCO, which has been carrying out this work, has increased the land level to 5.5 metres.

The Ulwe river has been diverted outside the airport boundary and the channel widened to 60 metres.

A source said the river diversion work would be completed in a week’s time, while the work of laying underground power cables is expected to be completed by December-end.

More than 85 per cent of project-affected villagers have been shifted and the rest are expected to vacate by June end. Ten villages have been impacted by the project and number of impacted families is around 2,600. CIDCO has offered plots to those whose houses and land have been acquired for the project. Those who lost their land have been given 22.5 per cent developed plots as compensation in vicinity of the airport.

BS





OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2019

Technology Partner  aaRKayeN Solutions