JSW update on new projects in 2013-14.
During the quarter, the Company has commissioned the Continuous Galvanising line of 0.40million tonne per annum, which is part of phase 1 of CRM2 Project at Vijayanagar works and the Pellet Pant &Coke oven plant at Dolvi works. In April 2014, the company has commissioned the Continuous Annealing Line of 0.95 million tonne per annum at CRM-2, Vijayanagar Works.
The implementation of other ongoing projects like, 2nd CAL of 0.95 million tonne per annum at CRM-2, Electrical Steel complex, SMS-3 and 2nd Bar Mill at Vijayanagar Works are in progress and is likely to complete as per schedule.