Published On:March 21 2013
Story Viewed 2732 Times
Alstom to supply componenets worth Rs. 573 Crore for Nabinagar thermal project
Alstom has been awarded the contract worth USD 85 million (approximately Rs 573 crore) by BHEL to supply components for three units of 660 MW boilers for the Bihar project.
Under the scope of the contract, Alstom will co-operate with BHEL in designing the boilers and supply identified pressure parts of the 660 MW supercritical boilers.
It will also assist BHEL with technical advisors during the erection and commissioning of the units. Key components will be manufactured in Alstom's manufacturing facilities in Wellsville and Concordia ( USA), as well as in Durgapur and Shahabad (India).
The units are expected to be commissioned by 2017-18