Coal Ministry PSUs are diversifying revenue streams by adding coal-based power capacity of 6,640 megawatts (MW), for which an investment of more than ₹60,300 crore has been planned. These capacities are expected to be commissioned by FY29.

The rationale is to encourage coal mining PSUs to diversify revenue streams to be future ready with strategies for not only thermal power plants (TPPs), but also installing solar and wind power.

A senior Coal Ministry official explained that with India’s power demand growing at over 6 per cent annually, coupled with a target of having a 500 GW non-fossil fuel capacity, TPPs would be required (in absence of cost-effective battery storage) to maintain integrity of the power grid.

Ministry advised Coal India (CIL) to find suitable de-coaled land for establishing pit-head TPPs. Setting up units at pithead is more cost-effective, with a tentatively fixed cost of around ₹2.5 a unit and a variable cost of about ₹1.25 per unit. Coal is likely to be surplus in the future and plan is to ensure sustainability in operations for CIL and NLC India (NLCIL) by setting up these TPPs, he added.

CIL, which accounts for almost 80 per cent of India’s coal production, is in the process of setting up two TPPs. First one is located near Amarkantak as a joint venture with the Madhya Pradesh government. The planned capacity is 660 MW with an estimated cost of ₹5,600 crore.CIL, which accounts for almost 80 per cent of India’s coal production, is in the process of setting up two TPPs. First one is located near Amarkantak as a joint venture with the Madhya Pradesh government. The planned capacity is 660 MW with an estimated cost of ₹5,600 crore.

It will be executed through a joint venture between CIL subsidiary, SECL, and Madhya Pradesh Power Generating Company. The work is expected to commence by the end of this financial year, with completion targeted for 2028.

Besides, Mahanadi Coal Fields (MCL), another CIL subsidiary, has set up Mahanadi Basin Power, as a fully owned subsidiary. MCL plans to establish a 1,600 MW TPP near its Basundhara Mines.

This pithead plant, with an estimated cost of ₹15,947 crore, has received interest from different States for 4,000 MW worth power purchase agreements (PPAs). Work is expected to begin around the middle of FY25 and targeted completion date is set for 2028.

Lignite miner NLCIL is setting up a 1,980 MW capacity TPP at Ghatampur, near Kanpur, at a cost of ₹19,406 crore. A joint venture with Uttar Pradesh, the project will supply 1478.28 MW to Uttar Pradesh and 492.72 MW to Assam. The first phase is expected to be commissioned by the end of this year.

Also, NLCIL has formulated plans to construct a 2,400 MW pit-head TPP at Talabira in Odisha. The project cost is estimated at ₹19,422 crore and it will supply 1,450 MW power to Tamil Nadu, 100 MW to Puducherry and 400 MW to Kerala. It is expected to begin by the end of this year and likely to be completed by FY29.

HBL





OUR OTHER PRODUCTS & SERVICES: Projects Database | Tenders Database | About Us | Contact Us | Terms of Use | Advertise with Us | Privacy Policy | Disclaimer | Feedback

This site is best viewed with a resolution of 1024x768 (or higher) and supports Microsoft Internet Explorer 4.0 (or higher)
Copyright © 2016-2026

Technology Partner - Pairscript Software